CCC Manzanillo III
Objective
Installation, configuration, local testing, and link testing of the equipment for the administrative, operational, control, and instrumentation networks of the project.
Project Description
Commissioning of the communications networks for the control, instrumentation, operational, and administrative areas of the MNZ III complex:
- Design of engineering and architectures for communications networks for both Transmission and Generation.
- Equipment selection without detailed specification provided by CFE.
- Coordination of personnel activities, as well as subcontractors.
- Configuration of equipment for links with CENACE, Administrative Network, Operational Network, and its management.
- Participation in clarification meetings and project briefings.
- Functionality testing of the equipment in general together with CENACE.
- Preparation of technical documentation for acceptance of completed work.
- Supply of fiber optic cables, installation, splicing, and OTDR and optical power tests.
- Supply of required equipment for special situations in the ECS system.
- Installation and configuration of FW equipment according to project needs.
- Design of heat maps for the installation of WiFi 7 APs.
- Supply and installation of patch cords and fiber jumpers.